Brokenwood Wines

Established in 1970, Brokenwood Wines in the Hunter Valley has evolved from a weekend venture for self-professed hobby winemakers into one of Australia’s most reputable wine labels.

Background

Brokenwood Wines were looking for a solution to reduce energy usage and operational costs across the business. Following a recommendation they engaged Shine On to complete an assessment of their site.

The project

After completing a full site assessment Shine On provided a comprehensive proposal outlining the savings that would be achieved through an upgrade to LED lighting. Shine On were engaged to upgrade the old lighting in the wine production areas.

Results

The results are outstanding! With a 77% reduction in their energy usage and costs and a payback period of less than 18 months, the customer is understandably very happy.

Brokenwood Wines following a LED upgrade with Shine On

Brokenwood Wines following a LED upgrade with Shine On


West Tamworth Tennis Club

West Tamworth Tennis Club has seven tennis courts that are used throughout the day and evening.

Background

West Tamworth Tennis Club wanted to improve the existing lighting experience for their players as well as reduce the amount of energy the courts consumed.

The project

Shine On provided thirty-five of our Caravel High Mast LED Floodlights. The Caravel has been specifically designed for outdoor court applications, providing even light distribution and an extremely low glare index.

Results

The tennis club is now saving 65% on their annual lighting energy costs with a 40% increase in the lighting levels seen on court.

Prior to upgrade the average lux across the seven courts was 274 lux with a target improvement of 28% (350 lux). The achieved results are a 40% improvement in lighting output with an average of 383 lux across the courts.

Needless to say, both the client and players are very happy with the results.

West Tamworth Tennis Club following an LED lighting upgrade with Shine On

West Tamworth Tennis Club following an LED lighting upgrade with Shine On


Embracia Aged Care

Embracia is family owned and operated for over 30 years and they are passionate about creating a warm, friendly and thriving community of residents.

Background

After having successfully upgraded their lights to LED with Shine On in 2017, Embracia wanted to take the next step to combat rising energy costs with energy generation.

The project

One of the key reasons Embracia chose to work with Shine On was our industry leading workmanship warranty and 5 year performance guarantee as well as their past positive experience working with us.

Being an aged care home, consideration was required of residents needs with little interruption and safety being of the utmost importance. Design and installation were also challenging due the design of the roof and building.

Results

The system produces approximately 115,671 kilowatts per annum which is equivalent to powering 17 average Australian homes. This means savings for Embracia Aged Care will be in the region of more than $900,000 over 25 years.

Embracia Aged Care following an LED lighting upgrade with Shine On

Embracia Aged Care following an LED lighting upgrade with Shine On


Omni Group

Omni Group is Australia’s leading packaging supplies and machinery innovator.

Background

Omni Group upgraded their warehouse with LED highbays from Shine On and with the quality still being as good as the day they were installed five years ago, they decided to also retrofit their showroom, printing room and office with Shine On LED lighting.

The project

Shine On assessed the areas to be upgraded and provided a comprehensive lighting design. The project commenced on the basis that installation would be completed during their business hours with no interruption to their operations. The installers were efficient and courteous to employee needs and completed the job without disruption to their work.

Results

The centre is now saving 62% on their annual lighting energy costs with a payback period of 38 months. They are amazed with the new lights, with a brighter working environment and impressive product displays.

Omni Group following an LED lighting upgrade with Shine On

Omni Group following an LED lighting upgrade with Shine On

Omni Group following an LED lighting upgrade with Shine On


Bloomfield Collieries

The Bloomfield mine is one of the Hunter Valley’s oldest, continuously running open-cut operations. Through steady growth and innovation the mine continues to produce quality coal products.

Background

Bloomfield Collieries wanted to upgrade to LED at their coal mining site in Ashtonfield to improve lighting quality and reduce energy and maintenance costs. It is also an important part of their environmental sustainability contributions. Shine On was selected due to the overall quality of our offering. In particular, quality products backed by long term warranties, a full turnkey solution, references from other large projects completed in the area and a locally available team.

The project

Prior to finalising the project, lighting designs and trials were undertaken to ensure everything would be completed to their requirements. Floodlights and highbay fittings were then installed in the main workshop, as well as floodlights in the carpark and highbays in the storage areas.

Results

The mine site is now saving 78% on their annual lighting energy costs with a payback period of only four months! They have found the new LEDs to be a massive improvement in terms of quality of light across all of the areas that have been upgraded.

Bloomfield Collieries mine following an LED lighting upgrade with Shine On

Bloomfield Collieries mine following an LED lighting upgrade with Shine On


Lane Cove Aquatic Leisure Centre

Lane Cove Aquatic Leisure Centre is home to a number of facilities including indoor and outdoor pools and a health and fitness club.

Background

Lane Cove Aquatic Leisure Centre wanted to upgrade their floodlights over the pool areas to LED. Their current floodlights were failing, expensive to run and, due to access issues, time consuming to repair. There were also safety concerns with dark areas due to failed lights. Shine On was sought based on a recommendation from an existing client.

The project

We completed the installation around the schedules of their customers throughout the day. We also had spotters on the ground to ensure safety. After the installation was completed, extensive testing was done to make sure the lights worked with their pre-existing computer control systems. In addition, some architectural lights that were costing money but not adding lighting to areas needed, were removed.

Results

The centre is now saving 80% on their annual lighting energy costs with a payback period of only 16 months. They love their new floodlights, with the increased lighting levels making the centre and pools look refreshed and clean. They’re also happy to be providing a higher level of safety for their customers and employees.

Lane Cove Aquatic Leisure Centre following an LED lighting upgrade with Shine On   Lane Cove Aquatic Leisure Centre following an LED lighting upgrade with Shine On

Lane Cove Aquatic Leisure Centre following an LED lighting upgrade with Shine On


John Herrod & Associates

John Herrod & Associates is a printing company that specialises in labels for the in-mould labelling process, supplying to some of the world’s biggest brands.

Background

Having upgraded their lights to LED with Shine On in 2015, John Herrod was looking for other ways to offset recent increases in electricity costs. Spurred on by a desire to increase efficiency and decrease their environmental footprint, solar power seemed like the natural progression.

The project

John Herrod had looked over a number of quotes before they entrusted Shine On once again to deliver the project. We provided a detailed feasibility report that included: a full review of their annual usage; solar irradiation data; comprehensive PV design and complete financial return expectations. The 99.84kW solar solution gave them access to upfront government subsidies while generating 15% of their annual power usage. The installation was successfully completed to a compressed time frame to meet client requirements.

Results

The system produces approximately 116,915 kilowatts per annum which is equivalent to powering 17 average Australian homes. This means savings for John Herrod will be in the region of more than $600,000 over 25 years.

John Herrod & Associates' solar installation by Shine On

John Herrod & Associates' solar installation by Shine On


Tyrrell’s Wines

Established in 1858, Tyrrell’s Wines is one of Australia’s most distinguished family-owned wine companies.

Background

Tyrrell’s were looking to upgrade the lights at their Pokolbin cellar door and surrounding buildings to combat rising energy costs, improve the lighting ambience in public areas and create a safer working environment.

The project

Before recommending a solution, we undertook a number of site visits to completely understand the client requirements and ensure we delivered the best possible outcome. The majority of the job involved replacing all fluorescent tubes with our Juko IP66 LED Battens and upgrading all energy-zapping 400 watt metal halides to our 110 watt Apollo UFO LED Highbay.

Results

Following installation, Tyrrell’s has saved 72% on their lighting energy bill, which equates to over $24,400 in savings in the first year and completely paid back within the same time! Importantly, the lighting within the site has improved significantly, creating a far better and brighter working environment.

Tyrrell's Wines following an LED lighting upgrade with Shine On     Tyrrell's Wines following an LED lighting upgrade with Shine On


Bega Cheese

Bega Cheese is an Australian dairy company that manufactures cheese, spreads and grocery ingredients.

Background

Bega were looking to upgrade their huge milk processing plant in Tatura Victoria to reduce their massive energy bills and to fix a number of failed, but not easily accessible highbays. Shine On was selected due to the market-leading lifetime ratings and warranties of our highbays and canopy lights and our unrivalled experience installing LED in food manufacturing facilities.

The project

Before recommending a solution, we undertook a number of lux simulations in key areas to ensure we exceeded AS1680 with the lowest possible wattage light. Our solution involved upgrading the old 400 watt metal halides in the food production areas to our 120 watt LED Canopy and in all other areas to our 97 watt H-Flux Mk4 LED Highbay. All floodlights were upgraded to various wattages of our Orbon Mk3 Floodlight. The interior lights included motion sensors to ensure they were only on when the areas were occupied, further increasing savings.

Results

Following installation the site now saves 84% on its lighting consumption, which will deliver 10 year savings of over $3.5 million and paid back within only 13 months!

Bega Cheese following an LED lighting upgrade with Shine On          Bega Cheese following an LED lighting upgrade with Shine On


Goodyear Autocare

Goodyear Autocare Parramatta is a multi-brand tire and automotive service retail shop and part of the Goodyear franchise: one of the world’s largest and most successful tyre companies.

Background

Goodyear were seeking to upgrade their lights to LED in the retail and workshop areas. They were looking to improve lighting outcomes with a more modern aesthetic look whilst also reducing their carbon footprint. Shine On was selected for this role due to our reliable and superior products and trusted working relationship.

The project

Before recommending a solution, we undertook a lighting design of the retail and workshop areas to ensure the lights were achieving the required standards. Our solution involved upgrading their old inefficient lights to market-leading Shine On LED battens and highbays.

Results

Now the site has been upgraded, it will save 78% on its lighting consumption, which will deliver 10 year savings of nearly $29,000. The upgrade has also resulted in a much brighter and safer working environment for Goodyear staff and customers.

Goodyear following an LED lighting upgrade with Shine On

Goodyear following an LED lighting upgrade with Shine On


CSL Behring

CSL Behring supplies an expanding portfolio of medicines to people in over 30 countries globally. They are one of the largest bio-pharmaceutical companies in the world.

Background

CSL Behring were looking to upgrade their lights to LED in the office and common areas at their Victorian head office. They were looking to improve lighting outcomes with a more modern aesthetic look whilst also reducing their carbon footprint. We were selected to complete the job as we had previously successfully upgraded their Parkville warehouse.

The project

Before recommending a solution, we undertook a lighting redesign of certain areas to ensure the lights were achieving the required standards. Our solution involved removing the old fluorescent light fittings and replacing these with far sleeker and more modern looking Omera Mk2 LED panels.

Results

Following completion of the upgrade, the site had far superior light levels with the added benefits of first year savings of over $25,715 a year with a payback period of just over three years.


Parramatta Plus Fitness

Parramatta Plus Fitness is part of a franchised chain of Plus Fitness gyms situated at over 180 convenient locations across Australia and New Zealand.

Background

Plus Fitness wanted to upgrade their lighting to LED to create a more modern look and uniformity of light and to reduce maintenance costs. Shine On was selected due to the quality of our panels and the significant financial benefits to be gained.

The project

Our solution involved removing the old fluorescent light fittings and replacing these with far sleeker and more modern looking Omera Mk2 LED Panels.

Results

Following completion of the upgrade, the site has saved 42% on their lighting bill. That equates to over $25,000 a year with a payback period of just six months! The owner was so impressed with the results that we have since been referred to another five Plus Fitness sites across Sydney.

Parra Plus Fitness upgraded with Shine On Omera Mk2 LED Panel